ELECTRICAL
INDUSTRY
SEBASTIAN BERNSTEIN L.
I. BACKGROUND
INFORMATION
1. THE
FIRST 50 YEARS: 1880-1930
The origins
of the electrical industry in Chile can betraced to the mid 1880s with the inauguration
of public lighting in Santiago'smain square (the Plaza de Armas). The
following half century producedimportant developments in this field; developments
launched by the privatesector.
During this
time period, a large number of public serviceelectrical companies were formed,
some of which later merged to form largerfirms. By the 1930's four key companies
had emerged: the Chilean ElectricalCompany (CHILECTRA), the General Industrial
Electrical Company (CGEI), theSouthern Electrical Society (SAESA) and the National
Electrical Force Company(CONAFE). Moreover, self-generation of electrical power
grew tremendously,in part as a response to the deficiencies of the public services
in providinga timely supply of energy to important industries and mining installations.
As of the
1930s, electrical development diminished significantly.The reasons behind this
reduction include the world economic crisis as wellas the setting of electrical
rates on the basis of political criteria andgrowing governmental regulations
which tended to check electrical companies'freedom of action.
2. THE
PERIOD BETWEEN 1940 AND 1973
As a result
of the lack of investment by private firmsin the electric industry, the State
elected to intervene actively throughthe Corporation for Fostering Production
(CORFO). Thus, physical developmentbetween 1940 and the end of the 1970s was
controlled through the implementationof the National Electrification Plan. This
program, initially formulatedby the Chilean Institute of Engineers, was studied
by CORFO and implementedessentially through ENDESA, a CORFO subsidiary, formed
in 1944. ENDESA subsequentlytook control of planning for development in the
electrical industry andreported its progress to CORFO and the Ministry of Finance.
The followingchart shows the general structure of the industry in 1940, the
startingpoint for the aforementioned Plan (Chart 1):
Table 1
Electrical Sector in 1940
| Installed Capacity | Public Service | 179 MW |
| Self generators | 308 MW | |
| Location of the installed | ||
| capacity | Northern Zone | 43% |
| Central Zone (Aconcagua-Linares) | 44% | |
| Southern Zone | 13% | |
| Type of generation | ||
| Hydro | 32% | |
| Thermal | 68% | |
| Gross annual generation | Public Service | 588 GWh |
| Self generators | 1365 GWh | |
| Gross per capita consumption | Public Service | 121 kWh/Hab |
| Self generators | 281 kWh/Hab | |
| Total | 402 kWh/Hab |
(1) Estimated
at 330 kWh/Inhab net. In comparison, in 1933the net kwh/inhab consumption ratio
in the USA was 1020, in Germany it totalled540 and in France the figure was
380.
The Plan's
foremost protagonist was ENDESA although theprivate CHILECTRA was also able
to participate, primarily during the 1960s,in the development of thermoelectric
power stations and electrical distributionin the metropolitan areas of Santiago
and Valparaíso. The ElectrificationPlan called primarily for the development
of hydroelectric plants in thecentral-southern portion of the country and the
construction of transmissionlines which would connect a series of electrical
systems which until thatpoint had operated in isolation.
In 1970, CHILECTRA
-- the company responsible for generating,transmitting and distributing electrical
power in the areas of Santiago,Valparaíso and Aconcagua -- was nationalized.
Therefore, by the early1970s the generation of practically all public service
electrical powerand a large portion of the distribution networks were in the
hands of theState.
The following
graph reflects the development of electricalgeneration in Chile for the period
1930-1990 (Graph 1):
Chart 1
Total Electrical Generation
(GWh)

The physical
and institutional development of Chile's electricalindustry was the result of
the evolution of the regulatory framework. Thus,there was growing confusion
over the notion of public service, in termsof electrical supply, with the active
participation of the State in thebusiness and the objectives assigned to the
industry (particularly in theperiod 1970-1973) which tended not to coincide
with the criteria which shouldguide an economic undertaking of this nature.
The following section is abrief summary of the history of regulations in Chile's
electrical industry.
3. HISTORY
OF THE REGULATORY FRAMEWORK
Initially,
the development of the electrical industry wasconducted quite freely, without
any special regulation. In 1904, legislationentitled "Prescriptions for
the Concession of Permits for the Installationof Electrical Companies in the
Republic" was approved. This 5-articlepiece of legislation was short and
simple: essentially, it granted concessionsto utilize public or fiscal possessions
for the installation of electricalnetworks and established security conditions
to avert danger to humans fromthese constructions.
In 1925, the
State began to take an increasingly activeregulatory role. The first "General
Law on Electrical Services"passed that year regulated concessions for the
use of water to be utilizedto generate electricity, as well as the use of public
property and compensationto private parties for the installation of transmissio
lines. Furthermore,an oversight organism was created to ensure compliance with
the law andestablish a formal linkage between businessmen and the State.
This legislation
referred explicitly to the proceduresfor setting rates: essentially, companies
were authorized to obtain 15%return on net fixed assets which could be set in
gold pesos, thereby providingan automatic indexation clause.
The second
version of this legislation was passed in 1931.Here, the State increased its
control through the Direction of ElectricalServices. In terms of rate control,
the fixed assets of the companies wereto be assessed every five years but new
rates could only be requested ifprofitability failed to reach 10% over 3 consecutive
years. This clause-- a significant set-back as compared to the 1925 regulations
-- was accompaniedby the elimination of the gold standard, thereby revoking
the automaticrate adjustability which had been inherent in the previous legislation.
The disincentives
contained in these regulations, combinedwith the international crisis of the
early 1930s and the repercussions forthe financing for new works, increasingly
led private companies to abandontheir participation in the development of the
industry.
As a result,
the State took charge of the generation andtransmission of electrical power,
while the private sector limited its activitiesto participating in distribution
and maintaining wholly-owned power stations.Planning for the system was conducted
centrally by ENDESA, with a high degreeof technification. Eletrical rates, particularly
as of the 1950s, were sufficientto provide adequate levels of revenue.
A statutory
decree passed in 1959 (DFL No. 4), establishedcriteria for the granting and
cessation of concessions, as well as on proceduresfor rate calculation. Tariffs
were to allow a profitability of 10% overnet fixed assets with annual re-adjustability
clauses for capital and theoption of temporary rate adjustment when fluctuations
over 10% in the costof primary components occurred. The legislation called for
the establishmentof a rate commission to be comprised of delegates named by
the Presidentof Chile, electrical companies, consumers and the Superintendency
of ElectricalServices.
DFL No. 4
established a clear framework for the electricalindustry and made it possible
for private firms, such as CHILECTRA, to developimportant thermoelectric projects
in the Santiago-Valparaíso areafor a total of 338 MW.
In 1966, the
regulations on electrical rates were modified.Henceforth, the Ministry of Economy
was required to approve any rate hikesproposed by the Tariff Commission. As
a result, political factors were broughtinto play in the rate-setting process
which served as an additional disincentiveto private industry. As noted earlier,
CHILECTRA was nationalized in 1970.
In 1971, prices
were frozen. The skyrocketing inflationregistered as of 1972 resulted in huge
operational deficits for both publicand private electrical firms. These difficulties
led multilateral banksto discontinue loans to the Chilean electrical industry,
effectively bringingdevelopment programs to a standstill.
II. GENERAL
ASPECTS OF THE NEW ELECTRICAL POLICY
1. SHORT-TERM
MEASURES
In the first
few years following 1974, a process of financialrecovery was instituted among
state-owned and private electrical firms.This process led primarily to the progressive
recovery of prices for electricalenergy. Management ofi state-owned enterprises
was rationalized and responsibilitieswhich could be better handled by the private
sector were transferred toprivate firms. Thus, the construction activities conducted
by ENDESA wereactually implemented by private contractors, as was the case with
otherservices such as transportation and repairs.
2. REMAINING
STRUCTURAL PROBLEMS
The changes
introduced in the period between 1974 and 1979contributed to the rationalization
and normalization of a large portionof the industry, but failed to attack the
roots of a series of structuralproblems which made it difficult to increase
efficiency and make managementof the electrical industry compatible with the
policies applicable to otherfields of economic activity. The following are among
the most importantproblems in this area:
- Preponderant
State participation in the industry: almost90% of generation, 100% of transmission
and 80% of distribution was in Statehands. This meant controlling resources
of some US$ 200 million per yearwhich competed directly with the State's priorities
in social areas.
- The practically
monopolistic role of ENDESA in the developmentof the industry. The possibility
the participation of the private sectoror other State entities in the formulation
of new projects -- particularlyin the area of electrical generation -- was limited.
- Control
was difficult: although the electrical companieswere overwhelmingly state-owned,
there was no effective control over theindustry; moreover, in terms of overall
energy-producing entities, therewere no appropriate mechanisms for coordination
among the various sub-sectors.In practice, the power of the large State firms
was greater than that ofthe governmental organizations charged with their oversight.
- Political
impositions on state-owned companies of un-profitableactivities, such as the
development of inappropriate projects or the hiringof excessive personnel.
- Generation
of technological monopolies and occupationalmonopolies at the technical level,
particularly in the fields of generationand transmission.
- Definition
of the role of state-owned companies: untilthe creation of the National Energy
Commission (NED) and the definitionof policies on the macro and sectoral levels
by the Office of National Planning(ODEPLAN) -- as well as the redefinition of
CORFO's responsibility in themanagement of its subsidiaries -- there was a certain
degree of confusionin the electrical industry as to the State's regulatory and
business roles.In effect, the largest state-owned firms fulfilled both roles,
creatingfrequent conflicts of interests between their objectives and those of
thecommunity as a whole.
- Inefficient
rates from the economic perspective: in essence,the rates based on ensuring
profitability over a portion of assets failedto recognize the costs associated
with production, transmission and distributionof electrical power. Thus, a system
of premiums for the most efficient companieswas not generated, nor did the most
inefficient firms pay the price fortheir extravagance as would occur in a competitive
market.
Furthermore,
the legislation failed to specify criteriafor the establishment of rates within
and among companies. This led to avast array of rates schedules among power
companies. Lastly, the enormouslyhigh inflation registered in Chile during the
early 1970s further servedto complicate the adjustment of rates in accordance
with accounting principles.
3. OVERALL
STRATEGY
The strategy
designed to deal with energy production --and electrical power in particular
-- was consistent with the general economicand social development policies adopted
during the mid 1970s. In essence,these measures sought to maximize social well-being
by introducing increasedefficiency into the industries in question within the
conceptual frameworkof a subsidiary role for the State.
Economic efficiency
is understood here as achieving anoptimum distribution of resources in the economy,
in direct reference toPareto's optimum.
The subsidiary
role of the State means that the governmentdoes not act so long as there are
intermediary individuals or organizationsin society which are capable of acting
on their own initiative. Moreover,the State should provide sufficient mechanisms
to ensure the basic needsof those individuals who are unable to do so for themselves,
so long asthis support does not curb the activities of other social actors who
arecapable of satisfying those needs efficiently.
In terms of energy, the subsidiary role of the State translatesinto the non-participation of the State in business activities relatingto the industry to the extent that said activities are or can be implementedby private entities. The State's participation, therefore, should focuson ensuring adequate service and coverage for the lowest income groups.
Among the
variety of mechanisms utilized in Chile to achievethese goals in terms of energy
production, the following are of particularimportance:
a. The clear
separation of the regulatory and business-relatedactivities of the State.
The regulatory
function was handed over to the NationalEnergy Commission (formed in 1978) and
the National Planning Office (ODEPLAN).
The NEC is
a decentralized advisory body which reportsdirectly to the President. It is
composed of a 7-member Council and presidedover by an Executive Secretary. The
Secretariat is responsible for the Commission'stechnical activities as well
as its administration.
ODEPLAN prepared,
in conjunction with other governmentalentities, its so-called annual "Ministerial
Programs," which establishedspecific goals in the field of defining the
"rules of the game"for public administration and for state-owned firms
in particular. In termsof energy, there was close collaboration between ODEPLAN
and the NEC.
The management
of the energy-producing state-owned companies,whose structures most often mimicked
private enterprises, was submittedto the Corporation for Fostering Development
(CORFO), a government-controlledentity which served, in essence, as a holding
company. As such, CORFO wasnot responsible for issuing regulations controlling
the industry, but ratherplayed a crucial role in re-organizing companies, controlling
their management,division and privatization.
b. In an effort
to maximize community benefits, the NECwas charged with coordinating the large-scale
investment decisions madeby state-owned electrica utilities. Once a large portion
of the industryhad been privatized, this central planning was replaced with
individualefforts undertaken by private companies.
c. Implementation
of institutional and legal adjustmentsin an effort to:
- Achieve efficient management within state-owned companiesand subject them to the same regulations as private firms.
- Open new
areas to the participation of the private sectorin electrical industry, either
through the creation of new companies orby privatizing those held by the State.
d. Subjecting
State participation in the evaluation ofenergy resources to strict socioeconomic
criteria and restraining Stateparticipation where other organizations could
effectively complete specificprojects.
e. Lastly,
one of the most decisive elements of the newpolicies was the formulation of
a realistic and efficient price system whichaccurately reflected the value of
electrical energy.
III. SPECIFIC
ASPECTS OF ELECTRICAL POLICY
1. CENTRALIZATION
VS. DECENTRALIZATION
Before delving
into the specifics of Chile's electricalpolicy, it is important to pause for
a moment to discuss a factor that wascrucially important in determining the
best strategy for continued developmentin this area: the level of decentralization
acceptable in the productionand distribution of electricity which, over the
previous 4 decades, hadbeen characterized in Chile by a high degree of centralization.
The questions
Chilean regulators asked themselves were:to what extent is possible and appropriate
to decentralize the generationand distribution of electrical energy? To what
extent can the industry bemade competitive and be privatized? What were the
real reasons behind centralizingand maintaining State control over these activities?
In the early stagesof the debate, serious consideration was given to the formulation
of a single,state-run company, following the French model. However, this proposal
wasdiscarded as it was quickly agreed that such a company would, for the reasonsnoted
earlier, go against the grain of the long-term economic activity policiesbeing
designed for Chile.
Thus, the
following elements were considered in the discussionover the need to retain
the levels of centralization on which the Chileanelectrical industry had been
constructed.
a. Economies
of Scale in Generation and Distribution
As demonstrated
through the comparison of hydroelectricprojects in Chile, the concept of an
economy of scale does not appear beapplicable to the generation of electricity.
Furthermore,
economies of scale are not important elementsin the growth of distribution companies.
In effect, a comparison of theaverage distribution costs of different sized
companies (defined as theratio between the yearly renewal costs plus annual
development expensesand the power delivered by the network) indicates that size
plays almostno role in cost. Thus, the presence or lack of economies of scale
in thegeneration and distribution of electrical energy is not significant.
Chart 2
Average Cost of Generation at Several
Hydroelectic
Plants in Chile

Chart 3
Average Distribution Costs

Once the need
for economies of scale had been discarded,the advantages of having a variety
of competing electrical generation anddistribution companies became apparent.
However, three problems remainedto be resolved:
- Investment
planning decisions, that is, the degree ofcentral coordination required to bring
generating plants on line. This problemis only relevant to the extent that the
projects comprising an optimum expansionplan are all of a structural nature,
thereby requiring coordination amongthem.
- Cooperation
in operations and in devising an efficientsystem of pricing for transfers among
utility companies. In Chile, the presenceof large reservoirs whose management
conditioned the operation of the entiresystem made coordination of such operations
particularly important.
- Establishing
fees for the use of transmission lines.
The measures
taken to address these problems will be discussedin a moment.
b. Private
Participation in a Decentralized Industry
Clearly, private
participation in the generation and distributionof electrical energy is possible
if: there is a demand for electrical power,profitable projects exist, processes
for planning works and setting rateson the basis of solid technical-economic
criteria are utilized, and if theso-called rules the game are stable and rational.
Furthermore, an environmentof decentralization favors the participation of the
private sector.
c. Competition
in the Electrical Industry
Competition
in operation can be achieved through the identificationand development of a
variety of power plant projects. These projects maybe implemented on the basis
of the different styles and criteria utilizedby companies to study, finance,
implement and operate power stations. Inlarge state-owned companies, on the
other hand, there is a tendency forpriorities to be placed on large projects
which are most often based onengineering criteria than on economic or financial
viability. Moreover,alternatives for such companies are frequently unavailable
and the Stateis obligated to support such large-scale projects.
In distribution,
concessionaires can compete in effortsto expand services with other private,
unregulated distribution services,such as rural electrification cooperatives.
Moreover, public service concessionscan be allowed to overlap in cases where
the quality of service by a givenconcessionaire fails to meet expectations.
Lastly, when the framework forestablishing distribution prices is based on a
the aggregate referentialvalue of a standard, model company (rather than on
expenses of individualdistribution firms), concessionaires end up competing
with the model company.
d. Decentralization,
Privatization and Efficiency
The decentralization
and privatization of electric companiesalso present advantages in terms of the
stability of the rules of the game.
- Government
officials are no longer faced with a singleinterlocutor but rather have several
sources of information. Thus, an environmentof greater competition is encouraged.
- The diversity
of companies and private participationconstitute good protection against lobbying
efforts by certain groups toobtain arbitrary reductions in rates.
- An incentive
is provided to improve technology, diversifytypes of employment and allow for
greater work-related mobility.
Furthermore,
privatization provides an important sourceof revenue for the Government without
having to tax the private sector.Privatization also requires diversification
in the ownership of installations,the development of capital markets and the
participation of strong institutionalinvestors such as pension funds, insurance
companies and the employees ofelectrical companies themselves.
De-concentration,
decentralization and privatization incomplex fields, such as the electrical
industry, require that policies bedesigned and implemented with great care.
The relationships between differentcompanies in a decentralized, privatized
framework mean that obligationsand reciprocal justifys -- particularly in the
area of pricing for energytransfers -- be clearly stipulated (whether they are
regulated or not) andthat coordination mechanisms be explicitly established.
2. INSTRUMENTS
FOR IMPLEMENTING ELECTRICAL POLICIES
In 1978, Chile
initiated a process aimed at an institutionalrestructuring of its electrical
industry in an effort to decentralize, enhanceefficiency, establish competition
and attract private participation. Ingeneral terms, electrical service was recognized
as just another type ofeconomic activity -- responding to the same stimuli as
other fields -- andtherefore the regulations implemented could not work against
natural forces.
The instruments
designed to achieve these objectives were:
- Rates set at marginal cost for small consumers and freedomof pricing for large end users.
- Division of large state-run companies and the separationof generation and distribution activities. Rates set at marginal cost forsupply by generators to distributors.
- Creation of a Economic Load Dispatch Center, a key elementin competition among generators.
- Design of a fee system applicable to common carrier transmissionsystems.
- Establishment of a new framework for generation planning.
- Changes in the types of financing available for investmentsand the drawing down of profits from state-owned firms.
- Clear definition of regulations, obligations and justifysof Public Service Distribution concessionaires.
- Authorization of the operation of non-regulated privatedistribution services.
- Privatization
of the majority of the electrical industry.
The following
is a brief description of each of the basiccomponents of these instruments.
2.1 RATES
Rates should
reflect the efficient costs of supplying electricity.Special emphasis was placed
on establishing efficient prices for transfersbetween and among the different
actors participating in the system, namely,generators, distributors and end
users.
The tariff
system was based on a clear distinction betweenelectrical supply with natural
monopolistic characteristics (such as electricaldistribution to a large number
of clients utilizing streets and roadways),for which regulated prices were established,
and areas in which it was possibleto create competitive conditions (supply to
large clients) for which freedomof pricing was established. The pricing system
for electrical energy wasdevised and implemented by the NEC in 1980 and was
described in detail inthe new legislation on Electricity approved in 1982.
These legal
bodies established four basic prices linkedto the marginal costs of supply:
- Prices for transfers among generators;
- Prices for sales between generators and distributors;
- Prices for clients of distribution companies;
- Freedom
of pricing for large end users (over 2MW).
Prices for
transfers among generators correspond to theshort-term marginal costs of the
electrical system and were calculated onthe basis of the Economic Load Dispatch
Center (ELDC). This matter willbe discussed in greater detail in a moment.
a. Rates
between Generators and Distributors
These rates,
known at "node" prices, are calculatedby the NEC as the marginal cost
needed to satisfy peak power (kW) and energy(kWh) at the sub-stations located
throughout the system. These marginalcosts are calculated for the generation-transmission
system on the basisof optimum development and operations.
The marginal
cost of peak power is based on the unit costof gas turbine installations (considered
the most economic fashion of supplyingpower during peak hours.)
The price
of energy is calculated as the short-term marginalcost of the expanded electrical
system operating under optimum conditions.In order to avoid fluctuations which
might affect the stability of the tariffto end users, a flexible average of
sort-term marginal costs for the following48 months is utilized. Projectred
short-term marginal costs are computedthrough an optimization model based on
dynamic programming, appropriatefor the multi-year management of Chile's Central
Interconnected System ofreservoirs.
The "node"
prices are calculated every 6 monthsand are expressed through indexation formulas
based on a variety of theprincipal cost components of electrical generation
and distribution (fuelcosts, reservoirs levels, demand and others). These formulas
make it possiblefor rates to be indexed automatically within any given semester.
b. Rates
for Clients of Distribution Companies
These prices
are calculated on the basis of two components:node prices and distribution costs
(known as the "aggregate cost ofdistribution").
The aggregate
cost of distribution is roughly equivalantto the ratio between annual capital
costs plus the operating cost of a "model"distribution network and
the peak power it delivers. Over time, it has becomeclear that these aggregate
costs are representative of the long-term marginalcost of distribution given
that practically no variation occurs as a resultof company size.
The aggregate
cost is calculated for a "model company,"that is, one of an optimum
size and efficient management operating in aarea defined on the basis of the
density of distribution areas. These areasare, in turn, divided into high, medium
and low density areas and the nation's23 concessionaires are classified in accordance
with this system.
The aggregate
cost is expressed in terms of three basiccomponents: fixed costs associated
with clients which are unrelated to consumption;investment, operation and maintenance
costs, as well as reduced use of distributioninstallations (associated with
the demand for power during peak hours);the cost of supplying power during non-peak
hours; and, lastly, losses associatedwith the distribution of energy.
This regulatory
framework does not recognize the expensesgenerated by each distribution company,
but rather those of a hypotheticalmodel company which serves as an incentive
for real firms to reduce theircosts. The aggregate costs are established every
four years and are expressedthrough formulas indexed in such a fashion as to
allow companies to adjusttheir rates accordingly.
c. Prices
for Large End Users
Sales to end
users of power over 2,000 kW are contractedfreely between electrical companies
and users. At present, approximately35% of Chile's public service energy is
provided in this fashion. The applicationof free pricing is based on the presence
of a number of generation-transmissioncompanies and the possibility of competition
among them (even when theymay use transmission systems belonging to third parties).
Furthermore,
such large clients have both the power tonegotiate and the ability to develop,
either on their own or in conjunctionwith other users, projects aimed at satisfying
their electrical needs whichwould compete with the services supplied by the
public utility companies.
It is important
to note that to a certain extent, the freepricing system serves as a guideline
for "node" prices. In effect,current legislation indicates that node
prices may not be more than 10%higher or lower than the free market rates for
the system at large.
2.2 DECENTRALIZING
STATE-OWNED COMPANIES
Chile's large,
vertically integrated, state-owned electriccompanies were separated into generation
and distribution firms (the latterwere also sub-divided into regional companies).
Thus, subsidiaries
of ENDESA and CHILECTRA were formed,as were new companies which depended on
CORFO. Chilectra was divided intothree sub-divisions, CHILGENER, was charged
with generating and transmittingenergy in the Santiago-Valparaíso area;
Chilectra Metropolitana,distributed electricity in Santiago; and Chilectra V
Región tookcharge of distributing electrical energy in Valparaíso
and the Aconcaguariver valley.
ENDESA was
transformed into a company dedicated exclusivelyto the generation of electricity
while its old Distribution Administrators,EMELAT (Atacama), EMEC (Coquimbo),
EMELIG (Ligua Valley), EMEL (Melipilla)and EMECO (Colchagua) became distribution
subsidiaries. Subsequently, manyof these companies located in rural areas merged.
ENDESA also
created generating subsidiaries, namely PULLINQUEand PILMAIQUEN S.A. (each with
a capacity of approximately 40 MW), COLBUNS.A. (490 MW). PEHUENCHE S.A. (500
MW) was formed as a subsidiary of CORFO.
In addition,
some ENDESA affiliates broke away to formindependent companies, as was the case
in the farthest-flung reaches ofthe country: ENDELNOR (Northern Chile), EDELAYSEN
(Aysen) and EDEMAG (Magellan).
2.3 ECONOMIC
LOAD DISPATCH CENTERS (ELDC)
Undoubtedly,
the coordination of the operations of a large,inter-connected system is a technical,
economic and political necessityif efficiency is to be achieved through the
decentralization and de-concentrationof the generation and distribution of electricity.
With this purpose inmind, the NEC designed the so-called Economic Load Dispatch
Center (ELDC)which primarily sought to:
- Ensure the viability of the electrical system;
- Ensure operations at a minimal cost for the system asa whole;
- Charge fees for transfers among companies generatorsin accordance with the system's short-term marginal costs;
- Establish
equal conditions for marketing the energy.
The ELDC was
conceived to:
- Plan the
operations of the existing system, consideringthe schedule for the incorporation
of power stations. The ELDC plans operationsover the long-term (5 years), medium-term
(1 year) and short-term (1 weekto 1 month), including operations for the following
day. In addition, theCenter calculates the short-term marginal costs associated
with optimumoperations and ascertains and assigns the cost of transfers of electricityamong
companies and ensures their payment to the owners of the transmissionsystem.
- Conduct
the operations of the system, considering exclusivelythe generation activities
of each company, independent of the conditionsunder which they sell their energy.
Thus, the Center did not take pricescontracted with end users into consideration.
- Plan operations.
However, the Center does not operatethe system on a real-time basis.
Small inter-connected
generators were not required to belongto the Center and were authorized to sign
contracts freely with larger generators.
This meant
that for planning purposes the ELDC was independentof the particular preferences
of each generator and made its decisions onthe basis of broadly accepted criteria:
reservoir level, price of coal andoil, demand, etc.
Prices for
transfers of energy among generators are establishedin accordance with short-term
kWh marginal costs as measured at the sub-stationwhere the transfer takes place.
Transfers
of peak power are established on the basis ofkW marginal costs, utilizing the
investment cost of gas turbines (as a reference)located at the most convenient
point on the system. Prices for these transfersare established in advance, in
January of each year.
In order to
keep generators from selling more power orenergy than their company has available,
contracts are inspected so as toensure that commitments do not exceed production
and/or supply contractedwith other generating companies. Prices for power supplied
through suchcontracts with outside companies are free to fluctuate. This tends
to limitover selling by generators.
It is important
to note that the ELDC does not purchaseenergy nor establish prices for end users
but rather serves as an intermediarybetween generators in order to enhance the
organization of their services.
2.4 FEES FOR
UTILIZING THE TRANSMISSION SYSTEM
Sharing of
the transmission system is a critical tool fora successful policy of competition
among generators of electrical energy.Given the importance of the transmission
system, the regulations establishinga fee structure for its use is contained
in the general Electrical Law.
Obviously,
the use of transmission lines owned by thirdparties for the transmission of
electrical energy requires that fees bepaid for this service. If economies of
scale did not exist, there wouldbe no problem in charging a general fee for
production and transmission(such fees would simply be the difference in rates
between the two endsof the line in use). However, the presence of economies
of scale in thissegment of the electrical industry means that the so-called
"tariffrevenue" (difference in rates at each end of the line) must
be supplemented.This need is even more evident when power stations generating
electricalenergy are brought on line which do not have contracts with end users
butmake use of the transmission system.
Thus, the
annual income received by the owner of the transmissionsystem must be supplemented
when third-party power stations make use ofthose installations. As a result,
a connection fee or "basic toll"is established. This toll is calculated
on the basis of the total supplementcorresponding to the "area of influence"
where the latter is definedas that portion of the system where the presence
of a power station resultsin alterations in the flow over those lines. The proportion
is calculatedas the ratio between the maximum power emitted by the owner of
the powerstation and the maximum power emitted by all of the users in the area
ofinfluence, including the owner of the transmission system.
Payment of
this toll enables the owner of the power stationto sell energy to end users
located at any point within the area of influencewithout the need to charge
an additional fee. When a power station doesnot have end user clients, the station
is authorized to sell its energythrough the ECDC at the price corresponding
to the short-term marginal costat the sub-station generating the energy.
2.5 PLANNING
Because of
their characteristics, distribution-orientedinvestment programs lend themselves
to full decentralization. That is, suchdecisions can be adopted independently
by each company. Nonetheless, a clearframework of justifys and requirements is
needed in order to ensure that activitiesin this area, which tend to form a
natural monopoly, actual serve the community'sinterests.
In generation
and transmission, however, large-scale projectstend to be of a structural nature
and therefore have a significant impacton the operation of existing and future
power stations. Thus, coordinationis extremely important in order to minimize
the total cost of supply, marginalexpenses and, eventually, the rates end users
pay for electricity. The exceptionsto this rule, however, are the small-scale
projects whose feasibility canbe independently evaluated through existing pricing
mechanisms.
The role of
the State in coordinating large-scale investmentprojects in these areas is important
in terms of both the impact these effortsmay have on rates and the position
the State adopts when confronted witha potential disequilibrium between supply
and demand.
When Chile's
electrical companies were owned by the State,proposals resulting from such planning
activities were obligatory. Withinthe framework of active private participation
in the industry, however,such planning is considered a recommendation.
Responsibility
for planning Chile's large-scale electricalgeneration projects has resided with
the NEC since its formation 1978. Theagency worked with companies generating
electrical power which were requiredto submit their expansion projects to the
Commission for consideration.These requirements remained in place until 1989,
when the privatizationprocess was finalized. As of that date, the NEC's findings
have been considered"recommendations."
Because the
electrical industry is a competitive one inwhich there is no direct relationship
between producer and consumer (transmissionlines owned by third parties can
be utilized), the new legislation did notrequire that electrical generation
services be provided. Moreover, the pricingsystems -- both free and regulated
-- were sufficiently attractive so asto ensure that such development activities
in fact took place without governmentintervention.
2.6 FINANCING
POWER PLANTS
Small and
mid-sized projects were initially conducted directlyby state-run companies and
work continued on them following privatization.In order to finance these projects,
a variety of mechanisms were utilized,including depreciation, and credits from
suppliers and multi-lateral lendinginstitutions (primarily the IDB) as well
as the so-called "reimbursablecontributions" electrical companies
received from new users.
Chile's largest
power stations (those generating over 200MW),were developed through the creation
of new CORFO subsidiaries. These companiesundertook the activities relating
to the development of the stations, utilizing,for the most part, a portion of
the engineering know-how accumulated throughENDESA, as was the case with COLBUN
S.A. and PEHUENCHE S.A. (500 MW each).Financing of these projects was structured
through minority capital contributionsmade by existing companies and CORFO,
as well as credits from suppliers,the IDB and IRDB.
A policy of
distributing the largest possible percentageof profits among shareholders was
established. While the State continuedto own the companies, such dividends naturally
went to the State. Obviously,this policy was designed to sustain a healthy financial
situation withinthe new companies. The exception to the rule in this case was
ENDESA itself.The company's enthusiastic use of favorable international market
conditionsjust prior to the economic crisis of 1981-1982 contributed heavily
to thenegative results on the firm's balance sheet.
In fact, ENDESA's
indebtedness was sustained at acceptablelevels through 1981. With the devaluation
of the Chilean currency in 1982,however, the situation became critical and special
measures were neededto resolve the company's financial woes. These measures
will be discussedin a moment.
The State's
policy of drawing down profits must be understoodwithin a context of maximum
flexibility in the use of revenue, taking intoaccount its fungibility and without
establishing re-investment requirements:an effort was made to keep the electrical
industry from becoming a "closedcircuit" where the revenue generated
was automatically re-investedin the industry itself. The concept was -- and
continues to be -- that theviability of each electrical project should be sustainable
on its own meritsand that financing for such ventures should be a separate matter.
2.7 ORGANIZATION
OF DISTRIBUTOR justifyS AND RESPONSIBILITIES
Although the
concept of competition is not foreign to electricaldistribution, it is clear
that, in practical terms, the field for such activitiesis limited. Thus, a system
of pricing and quality regulation needed to beestablished to ensure adequate
supply of electrical energy at a reasonablecost. Toward this end, geographic
areas were outlined for distribution concessionsand the responsibilities and
justifys of each of the distributors were established.
Legislation
was approved calling for "Concessionsof Public Service Distribution"
for electrical energy in the establishment,operation and use of public service
distribution networks.
The concession
defines a framework for the justifys and responsibilitiesof distribution companies.
The former include the justify to utilize publicgoods and private property, the
justify to a fair rate (but which does notsubsidize inefficiencies), and the justify
to request that users contributeto the financing of the expansion of distribution
installations as wellas increasing the capacity of existing installations for
electrical generation,transmission and distribution. These contributions must
be reimbursableand are therefore unrelated to the rates established for services.
Among the
latter, companies are required to provide serviceto any person or institution
requesting service within the concession areaand to comply with the regulations
governing service quality.
Users located
outside the concession area are authorized,by law, to link up with the concessionaires
installations through privateor third party lines. The price of energy at the
contact point is the sameas throughout the rest of the concession area.
The time-frame
granted for each concession is unlimited.However, concessions can be canceled
if the quality of service falls belowacceptable levels. Prior to cancellation,
reminders and fines must be issued.
2.8 THE PRIVATE
SECTOR
The legislation
allows for the private sector to engagein non-regulated distribution activities.
A good example of this participationhas been the activities of rural electrification
cooperatives and small-scaledistribution companies. These services are not regulated
in either qualityor price.
When non-regulated
services require the use of public landsto string lines, governmental authorization
must be obtained.
IV. PRIVATIZATION
OF THE ELECTRICAL INDUSTRY
The privatization
of the electrical industry -- fosteredby the need for coherence in the framework
of socioeconomic developmentimplemented in Chile as of late 1973 -- was conducted
with considerablecare and pragmatism, particularly in terms of the speed with
which changesoccurred. In fact, the earliest privatizations did not occur until
1980and the process was not completed until early 1990. The measures taken inthis
field were adopted over time, and care was taken to respect institutional,political
and financial situations which arose along the way. Frequently,these situations
meant that strategies which had initially appeared viablehad to be altered and,
in fact, not all of Chile's electrical companieswere privatized.
It is important
to note that in the early years, therewas no consensus within the government
as to the advantages of privatizingan industry considered of strategic importance.
These initial doubts meantthat the process was conducted slowly. Solutions were
found to the industry'sfinancial problems and many people within the government
who felt that theindustry functioned efficiently opposed its privatization.
The primary problem,however, continued to be one of definitions. In terms of
efficiency, onemust not, obviously, confuse the efficiency of a company's personnel
--who may be capable and the most appropriate individuals for the job -- withthe
efficiency in executing specific tasks on the macro level of a state-ownedcompany
subjected to pressures, obligations and distortions which, in effect,impact
negatively on its management.
It was also
clear that the incorporation of private capitalinto the electrical industry
would not be trouble-free; it was no longera matter of normalizing the situation
of companies which had been nationalizedduring the previous administration,
but rather a shift in the overall focusof development policy. As a result, opposition
to the privatization processemerged in a variety of quarters:
- From elements within the government itself, who fearedloosing the ability to manage the industry politically.
- From company employees who feared for their jobs andthe so-called "social achievements" (benefit packages) which werefrequently much more attractive than those of the rest of the nation's workers.
- From company professionals and executives who, to a certainextent, controlled the day-to-day operations of the companies as a resultof the weak, rotating, directors appointed by the State.
- From extensive sectors within the Armed Forces whichperceived the electrical industry as being of particular strategic importance.
- From the political opposition, imbibed primarily witha statist culture and even from within the ranks of the government's supportersfrom those who feared taking a step of this magnitude.
- From some
business groups who perceived state-owned electricalcompanies as a vehicle for
obtaining subsidies through prices.
In any case,
it was clear that privatization required,in addition to a clear definition of
the rules of the game, the presenceof strong, important capital markets. The
emergence of such markets in Chilewas closely linked to the participation of
institutional investors arisingfrom the reforms implemented in the nation's
social security system. Inessence, the Pension Administration Funds (AFPs) which
managed the individualcapitalization funds of the nation's work force became
the largest singleinvestors in the privatized electrical system. Thus, AFPs
and other institutionalinvestors, such as insurance companies, the employees
of the electricalindustry themselves, and foreign investors (operating through
debt conversionmechanisms) became key actors in the privatization process.
As a result,
two paths for privatization were identified:sale of entire companies to individual
investors and "share packages"to institutional investors; and the
widespread, broad sale of smaller packetsto individuals through so-called "popular
capitalism."
As noted earlier,
a prerequisite for privatization wasthe establishment of clear rules of the
game -- regulations, obligationsand justifys, rates, guarantees on the justify to
property, etc. -- that wereboth transparent and grounded in sound technical
and economic analyses.
Another prerequisite
was transparency in the process ofselling shares; except in those cases where
the price of the shares wasnegotiated directly with employees (most often at
a rate set in accordancewith prices on the stock market). The sale of shares
in the electrical companieswas done through public bidding or through the auctioning
off of "sharepackets" on the local stock market.
During the
early stages of the privatization process, theargument most often given to oppose
these sales (in addition to those ofa purely ideological nature) had to do with
the prices at which the shareswere sold. Thus, arguments such as the following
were heard:
a. The State is selling property at prices below theirbook value. Thus, the argument goes, the government is "giving away"national property to a few select individuals. The error in this logic isclear: assets are worth the cash flow they can generate (this may bear norelationship to the book value).
b. The price charged for the installations is lower thansimilar facilities being built by the State; thus, national patrimony isbeing given away to the private sector. Again, there is a conceptual errorin this argument which is similar to the preceding one: if rates are setbelow costs, the flow of future income -- and therefore the economic worthof the installations -- may be much lower than the cost of similar facilitiesunder construction. This example serves to reinforce the importance of establishinga rational price system prior to privatization.
c. An argument
was made that if the private sector wishedto participate in the electrical industry,
it should be willing to makeits investments under the same conditions as the
State, that is, with lowrates of return (given that electricity is a public
utility). The conceptualerror continues to be the same: discount rates -- linked
to the cost ofmoney -- are set by the economy, just like any other price; the
State cannotimpose a discount rate below what the market stipulates for the
service.
Nonetheless,
it is clear that the State, upon privatizing,cannot accept just any discount
rate; setting this component -- which tendsto diminish as public trust in the
system increases -- is clearly one ofthe most delicate aspects of the privatization
process. The indicationsof confidence exuded by the State itself, as well as
the stability and rationalityof the regulations affecting the industry, are
therefore the keys to a successfulprivatization process.
The first
privatizations in Chile consisted of the publicsale of two ENDESA distribution
subsidiaries, SAESA and FRONTEL in 1980.Both companies were acquired by the
COPEC conglomerate.
From 1980
through 1983, almost no progress was made inthis area as a result of opposition
within CORFO to the privatization ofits largest subsidiaries, ENDESA and CHILECTRA.
Progress was made, however,in the formation of regional distribution companies
stemming off from ENDESAand in the break up of CHILECTRA into local subsidiary
companies.
In order to
continue progressing toward privatization,the NEC issued regulations requiring
that the reimbursable financial contributionscompanies were authorized to request
of new clients be paid back in companystock. Through this procedure, the public
became more aware of the presenceand behavior of electric company paper on the
stock market. Between 8 and10% of two Chilectra distributors were privatized
in this fashion.
Between 1983
and 1987, 3 small-scale hydroelectric plantsbelonging to Chilectra-Generating
(CHILGENER, for a total of some 20 MW)were sold through public bids. In addition,
PILMAIQUEN (35 MW) and Pullinque(49 MW), both ENDESA-owned stations which had
been transformed into subsidiarycompanies, were also privatized through this
mechanism.
Although a
large number of interested parties participatedin the bidding process, the properties
were eventually sold to Banker'sTrust (whose offer of some US$21 million for
PILMAIQUEN bettered those offive other contenders) and the Fernández
business group, associatedwith the Rural Electrification Cooperatives (who paid
some US$31 millionfor Pullinque). It is important to note that the sale of these
power stationsincluded a temporary option for the companies themselves to purchase
theenergy produced. This arrangement was based on the system's marginal costs,with
discounts of approximately 10% for the use of transmission lines andcharges
for frequency regulation.
Following
those sales, privatizations in Chile picked upspeed with the full sale of Chilectra
Metropolitana, Chilectra V Regiónand Chilectra-Generating. Employees
were particularly active in acquiringshares through the early withdrawal of
retirement funds. In addition, AFPsand banks invested heavily, the latter through
such mechanisms as debt conversionand swaps.
In order to
privatize ENDESA, the company's financial problems-- arising from its indebtedness
-- needed to be solved. It is importantto note that with the devaluation of
Chilean currency, a so-called "preferential"exchange rate for the
dollar had been established to avoid excessive lossesfor domestic companies
holding loans in U.S. currency. The "preferential"rate was set at
a mid-point between pre and post-devaluation levels andwas adjusted over time
so as to match, eventually, the real value of foreigncurrency in the Chilean
market.
In 1985, the
preferential rate for the dollar was eliminated,and ENDESA was left with losses
totaling some 360 million dollars. The debtwas absorbed through a reduction
in the firm's capital holdings. This proceduremade it possible for ENDESA to
continue to make profit payments on its shares.
With the patrimonial
absorption of this loss, the company'sfinancial position -- although not its
operational conditions -- progressivelyweakened. By the end of 1985, in fact,
its debt/capital ratio had risento 2.3.
As a result,
the Chilean government decided to adopt twoconcurrent measures: first, the Colbún-Machicura
power station, whichbelonged to ENDESA, was transferred to CORFO as COLBUN S.A.
The debt/capitalratio of the new company was 1.5; second, 500 million dollars
worth of ENDESAdebt were capitalized, leaving the company with a healthy debt/capital
ratioof under 1.0.
It is important
to note that, from the State's perspective(that is, in CORFO's rather than ENDESA's
view), this capitalization didnot produce tangible any changes, given that ENDESA's
debt belonged, inconsolidated terms, to CORFO. Nonetheless, it was clear that
the improvementin ENDESA's indebtedness would improve the company's position
via-a-visprivatization. Moreover, in terms of obtaining a better selling price
forENDESA, the capitalization proved to be important given that investors perceivedthe
risk of investing in a financially healthy company as significantlylower than
that of investing in a financially troubled firm.
The privatization
of ENDESA was conducted through the saleof "share packets" to AFPs,
employees and, most importantly, throughso-called "popular capitalism."
The latter format consisted ofsales of discounted shares (calculated on the
basis of stock market rates)to the public at large. The number of shares an
individual could acquirewas limited, and the credit extended for such purchases
was favorable. Asa result, the privatization process was completed even faster
than originallyprojected.
V. RESULTS
OF THE NEW POLICIES
1. GENERAL
ASPECTS
The policy
modifications and privatization processes introducedin the electrical industry
are entirely too recent to provide conclusivequantitative results.
Moreover,
such an analysis is further complicated by thefact that the privatization was
preceded by a complete restructuring ofthe industry. Thus, the question is,
what portion of the results can beattributed directly to restructuring, even
within the state-dominated framework,and what portion resulted exclusively from
privatization?
These questions
are not easily answered. Nonetheless, itis possible, from a qualitative perspective,
to formulate some conclusionson the results of the overall process conducted
in Chile. We will brieflyreview the behavior of the industry in terms of its
financial position,level of operational efficiency and the level of stability
of the currentrules of the game. Lastly, we will look into the challenges facing
in industryin years to come.
2. FINANCIAL
STANDING OF ELECTRIC COMPANIES
First, let
us compare the standing of Chilean electriccompanies with those of other Latin
American nations (many of which arefacing crisis situations) and those of developed
nations. From this comparison,the Chilean industry appears to be on solid ground,
both financially andin terms of operations, despite some persistent problems
which will be discussedin greater detail in a moment. (Charts 4 and 5).
Chart 4
ENDESA
Chart 5
CHILMETRO

The data indicates
a important evolution in the key variablesfor Chile's primary electric companies,
including:
- Profits: operational and non-operational, balance andaccounting patrimony.
- Profitability: defined as operating profits over fixednet assets (gross depreciated fixed assets).
- Profitability:
defined as operational results plus depreciationdivided by gross fixed assets.
This variable is similar to an internal rateof return on the investments conducted
to the extent that the gross fixedassets are not overly distorted by the worth
of new installations.
Important
fluctuations can be seen in the accounting profitability,which result primarily
from external factors such as currency devaluations.The devaluations led to
significant non-operational losses in 1982 and 1985and their impact was particularly
strong among the firms generating electricalpower (which tend to hold most of
their debt in foreign currency.)
The current
rates of profitability for Chile's primarysuppliers of electrical power are
given in greater detail in the chartson the following pages.
In addition,
these charts show clearly that ENERSIS isnot only a holding corporation for
distributors, but also owns shares inENDESA (some 12%) and has subsidiaries
dealing in real estate and services.Thus, the overall results for the company
are, in truth, not limited todistribution activities, even the latter do compose
the bulk of the firm'sbusiness dealings.
Moreover,
the data makes it clear that the operating profitabilityof distribution companies
tend to be higher than those of generators interms of fixed net assets. This
is due to the fact that the accounting depreciationsaccumulated by distributors,
in terms of gross assets, are much greaterthan those of generation companies.
Thus, the result is more of an accountingeffect than an economic one.
It is also
important to note that, in 1991, the profitabilityof the two largest generators
was even greater than in 1989 and 1990 (inthose years, Chile was affected by
a severe drought which limited results.)Moreover, in 1990 ENDESA brought a new
hydroelectric power station (Canutillar,145 MW) on line. The energy produced
at that plant will not affect the datauntil 1991 even though the investments
were completed in 1990. A similarsituation arises with other stations being
brought into service, such asPehuenche, a 500 MW station developed by an ENDESA
subsidiary, and Alfalfal,a 160 MW station under construction by CHILGENER. Both
plants were expectedto be operational by late 1991.
In any case,
it is clear that the distributors presenta higher rate of return (measured as
net operatioal income plus depreciationover gross fixed assets). However, it
is interesting to note that for recentprojects and those under construction,
that rate is similar to those achievedby distribution companies (8-18%). (See
Tables 2 and 3 below).
Table 2
FINANCIAL INDICATORS
(US$ per
year) 2 GENERATING FIRMS
| COMPANY | OPERATION | 1988 | 1989 | 1990 |
| ENDESA | Operational Income | 155.75 | 114.63 | 121.14 |
| Profit | 178.52 | 105.94 | 103.99 | |
| Depreciation | 56.38 | 56.14 | 65.12 | |
| Installed | Net Assets | 1,706.55 | 1,771.85 | 2.110.39 |
| capacity 1990 | Gross Assets | 2,629.22 | 2,753.05 | 3.290.60 |
| 2050 MW | Patrimony | 1,445.77 | 1,458.17 | 1.697.89 |
| Debt | 686.94 | 724.94 | 824.35 | |
| Liab./patrim. | 47.5% | 49.7% | 48.6% | |
| Profit/patrim. | 12.3% | 7.3% | 6.1% | |
| Op.inc./net fix. assets | 9.1% | 6.5% | 5.7% | |
| Op.inc,depr/gross assets | 8.1% | 6.2% | 5.7% | |
| CHILGENER | Operational Income | 23.07 | 23.66 | 39.66 |
| Profit | 22.13 | 24.73 | 32.55 | |
| Depreciation | 10.32 | 10.60 | 12.57 | |
| Installed | Net Assets | 305.41 | 402.83 | 556.33 |
| capacity 1990 | Gross Assets | 543.07 | 652.55 | 853.59 |
| 570 MW | Patrimony | 296.44 | 309.53 | 364.73 |
| Debt | 58.86 | 145.74 | 222.19 | |
| Liab../patrim. | 19.9% | 47.1% | 60.9% | |
| Profit/patrim. | 7.5% | 8.0% | 8.9% | |
| Op.inc/net fix. assets | 7.6% | 5.9% | 7.1% | |
| Op.inc.+depr./gross assets | 6.1% | 5.2% | 6.1% |
Table 3
FINANCIAL INDICATORS
(US$ per year) 2 DISTRIBUTION FIRMS
| EMPRESA | RUBRO | 1989 | 1990 |
| CHILQUINTA | Resultado operacional | 8.89 | 9.88 |
| Utilidad | 9.58 | 11.11 | |
| 280.000 | Depreciación | 2.49 | 2.65 |
| clientes | Activo neto | 43.78 | 51.85 |
| Activo bruto | 108.42 | 127.82 | |
| Patrimonio | 52.11 | 60.32 | |
| Deuda LP | 1.74 | 2.03 | |
| Pasiv. LP/patrim. | 3.3% | 3.4% | |
| Util/patrim. | 18.4% | 18.4% | |
| Res.oper./act.fijo neto | 20.3% | 19.1% | |
| Res.oper.+depr./act bruto | 10.5% | 9.8% | |
| ENERSIS | Resultado operacional | 46.26 | 52.89 |
| Utilidad | 53.30 | 93.81 | |
| Depreciación | 11.27 | 15.84 | |
| 1.100.000 | Activo neto | 230.70 | 272.83 |
| clientes | Activo bruto | 458.78 | 549.00 |
| Patrimonio | 245.25 | 316.22 | |
| Deuda LP | 28.69 | 70.47 | |
| Pasiv. LP/patrim. | 11.7% | 22.3% | |
| Util/patrim. | 21.7% | 29.7% | |
| Res.oper./act.fijo neto | 20.1% | 9.4% | |
| Res.oper.+depr./act bruto | 12.5% | 12.5% |
3. EFFICIENCY
A second aspect
of the evolution of Chile's electricalindustry in recent years is the overall
improvement in efficiency, as demonstratedby the following:
- Low rates
as compared to nations where the industry operatesnormally. Even at the Latin
American level, where there has been a traditionof subsidizing consumer consumption
in a variety of fashions, Chile's ratesmeet the average. The following tables
show typical rates for residentialand industrial power in foreign countries
and in three areas of Chile: north(thermoelectric generation based on oil and
coal); central (hydroelectric)and south (thermal generation based on natural
gas). (See Tables 5 and 6).
Table 4
AVERAGE RESIDENTIAL RATES
(US$/kWh)
| Country | Residential |
| 100 KWh | |
| West Germany | 20.63 |
| Belgium | 19.60 |
| Japan | 19.17 |
| Spain | 15.66 |
| Austria | 14.63 |
| Northern Chile (Emelari) | 14.39 |
| France | 14.38 |
| U.K. | 14.04 |
| Argentina | 13.99 |
| Switzerland | 12.82 |
| Netherlands | 12.46 |
| Portugal | 12.40 |
| Canada | 11.93 |
| Central Chile (Chilmetro) | 10.89 |
| Italy | 10.25 |
| Greece | 9.37 |
| Southern Chile (Edelmag) | 9.16 |
| Sweden | 8.72 |
| Brazil | 8.60 |
| Morocco | 6.71 |
| Uruguay | 6.53 |
| Bolivia | 4.97 |
| Paraguay | 4.34 |
| Costa Rica | 4.24 |
| Mexico | 4.08 |
| Colombia | 2.62 |
| Ecuador | 1.95 |
| Venezuela | 1.62 |
| Peru | 0.51 |
Note: - Includes taxes. As of 6/90
Source: - Unión Internacional de Productores y Distribuidoresde Energía Eléctrica. (UNIDEPE)
Chilectra Metropolitana (Poll dated 1/89)
- Sistema de Información Económico Energéticode la Organización
Latinoamericana
de Energía (SIEE-OLADE) (Poll dated6/90)
AVERAGE INDUSTRIAL RATES
(US$/kWh)
| Country | Industrial rate |
| (excluding Latin Amer.) | Pot: 500 kW |
| FC: 45,7% | |
| Japan | 9.70 |
| W. Germany | 9.19 |
| Morocco | 8.85 |
| Italy | 7.97 |
| Spain | 7.89 |
| Austria | 7.19 |
| Portugal | 6.62 |
| U.K. | 6.51 |
| Belgium | 6.43 |
| Northern Chile (Emelari) | 6.27 |
| Greece | 5.95 |
| France | 5.49 |
| Switzerland | 5.35 |
| Netherlands | 5.02 |
| Sweden | 4.30 |
| Central Chile (Chilmetro) | 4.09 |
| Canada | 3.84 |
| Southern Chile (Edelmag) | 2.99 |
AVERAGE INDUSTRIAL RATES
(US$KWH)
| Country | Industrial rate |
| (Latin America) | FC: OLADE |
| Argentina | 14.47 |
| Mexico | 7.30 |
| Costa Rica | 6.56 |
| Chile | 6.56 |
| Peru | 6.37 |
| Uruguay | 6.07 |
| Brazil | 5.61 |
| Colombia | 5.52 |
| Bolivia | 5.19 |
| Ecuador | 3.59 |
| Paraguay | 3.42 |
| Venezuela | 2.87 |
Theses figures
indicate that the healthy financial conditionof Chile's electric companies is
not the result of high rates, but ratherof sound management.
- The efficient
and rational use of energy: the pricingsystem, not only in terms of electricity,
but for other types of energyas well (particularly liquid fuels), has provided
an incentive for the properallocation of energy products. Thus, although the
utilization of electricityin Chile is relatively high (1374 kWh/resident in
1989), use is concentratedin areas where it is economically viable. As a result,
the inefficient useof electricity in such areas as heating, water heaters and,
above all, kitchenstoves, is not a problem in Chile given that there are more
cost-efficienttypes of energy available for these purposes and the appropriateness
ofthe pricing policies for such products. In some Latin American countries,the
use of electricity in heating water and kitchen stoves -- as a resultof price
distortions -- constitutes a serious problem.
- Some indicators,
such as the evolution of the ratio betweenthe number of company employees and
energy sold, bear further testimonyto the productivity of Chilean firms. Chart
6 demonstrates this evolution.
Chart 6
Number of Workers per Amount of Energy Soldor Generated

- Competition
has become the catalyst for further developmentsin the electrical generation
industry in Chile. This competition has beenreflected in recent years in the
growing number of occasions on which largeindustrial and mining complexes call
for public bids to supply them withelectricity.
- In terms
of service, quality and sensitivity toward publicimage, important progress has
been made. In fact, current legislation callsfor periodic polls to be taken
among clients in order to enable both companiesand government officials to evaluate
the performance of concessionairesin terms of service quality. Thus, important
firms, such as Chilectra Metropolitana,have completely revamped their customer
service and billing systems andimplemented policies aimed at providing electrical
installations quickly(24 hours after a request is filed for small consumers
whose installationsdo not require that the network be expanded, and a maximum
of 1 week inall other cases).
Coverage in
Chile is high by Latin American standards.In 1987, for example a poll among
low income sectors (CASEN) showed thefollowing electrical coverage rates for
the nation as a whole:
| Urban Area | 97.9% |
| Rural Area | 62.0% |
| Total | 91.4% |
Source: El
Sector Energía en Chile. CNE, 1989
Estimates indicate that improvements have continued to